For schools and public buildings with no connection to the grid - connection to electricity through the installation of photo-voltaic panels and an electricity storage system, and other local system.

 

  • Alfoura educational center - an autonomous water purification facility, carried out by the Lagoona Innovation company, began operating in November 2022. The purified water is expected to be used to create a green space and park for to the residents of the village.

  • Elementary school in Bir Hadaj - installation of an off-grid solar system that includes storage, to replace a diesel generator. Budget approved by the Ministry of Energy. Designated output:  220 KW with a storage capacity of 400 KWH.

Planned completion date: mid-2023

  • Elementary school in Rahma - installation of an off-grid solar system that includes storage, to replace a diesel generator. Budget approved by the Ministry of Energy. Also students and staff will participate in an educational program about sustainable energy.
    Designated output:  175 KW with a storage capacity of 400 KWH.

Planned completion date: mid-2023

  • Elementary school in Abutlul - installation of an off-grid solar system that includes storage, to replace a diesel generator. Budget approved by the Ministry of Energy. Also students and staff will participate in an educational program about sustainable energy.
    Designated output:  240 KW with a storage capacity of 400 KWH.

Planned completion date: mid-2023